Project

Chiltern Valley to Koonoomoo Gas Transmission Pipeline

113 km of 150mm and 200mm dia steel gas pipe

Project Details

LOCATION

Cobram, VIC

PROJECT VALUE

1.5m

YEAR

1998

CLIENT

Minson Construction

Related Projects

Santos Limited

Roma West 2B Gathering Project

This particular section included gas and water gathering pipelines, along with the added complexity of installation of HV & FOC reticulation, often commingled within the trenches with the PE Gas & Water pipelines.

Pneumatic testing was progressively completed in five defined sections, allowing a sequenced handover of the asset to commence early gas extraction.

Completed on time and on budget, with zero defects, despite significant challenges of slow rock excavation and inclement weather.

Westside Corporation

Meridian Seamgas Trunklines

Mitchell was engaged on a Lump Sum EPC basis:

Engineer: including detail design of the pipeline alignments, profiles, road, waterway & service crossings, vents & drains, taking into account landholder constraints, endangered habitat and access issues, and SMS all to APGA CSG Gathering code.

Procure: including the purchase, transport, storage and correct dispatch of all materials and external services providers.

Construct: Install, test and commission the pipelines, and handover As Built GIS and complete MDR.