Project

Rising Main No.1

2km of 375mm DICL, under road bore & assoc. Works

Project Details

LOCATION

Mango Hill, QLD

PROJECT VALUE

1.2m

YEAR

2001

CLIENT

Lend Lease Developments

Related Projects

Grampians Wimmera Mallee Water

Wimmera Mallee Pipeline Project

Major construction challenges included major river crossings, a variety of cultural heritage sites and liaising with some 4,000 property owners.

Mitchell designed and constructed six of the seven supply systems in just over 3 years, delivering the project 6 years ahead of the original 10 year time frame.

Mitchell’s safety performance on the project was outstanding, completing 900,000 manhours without a single LTI.

Santos Limited

Roma West 2B Gathering Project

This particular section included gas and water gathering pipelines, along with the added complexity of installation of HV & FOC reticulation, often commingled within the trenches with the PE Gas & Water pipelines.

Pneumatic testing was progressively completed in five defined sections, allowing a sequenced handover of the asset to commence early gas extraction.

Completed on time and on budget, with zero defects, despite significant challenges of slow rock excavation and inclement weather.