GLNG – Fairview CSG Gathering Lines

440km

Pipelines

$32m

Contract Value

Zero

LTI’s

DN800

Pipeline Diameter

Mitchell were awarded the contract for completion of 440km DN63 to DN800 Gathering Pipelines for Santos. In addition to the pipelines, Mitchell carried out civil works for completions of HSC04 and HSC05 hubs after the plant became live and under strict permit systems. The civils included procurement and construction of road pavements, drainage, bituminous sealing, concrete works and steel works.

Project Details

  • Major Tie ins
  • Live Digs & connections
  • Pneumatic strength and leak testing
  • Completion of PE pipelines
  • Replacement of GRE pipeline with SDR7.4 PE
  • Completion of Steel pipeline reinstatement
  • CP commissioning
  • Low Point Drains
  • High Point Vents
  • Golden Welds
  • Reinstatement
  • Test Packs
  • Material Data Register
  • Quality documents turnover

LOCATION

Injune, QLD

PROJECT VALUE

32m

YEAR

2014

CLIENT

Santos Limited

Related Projects

Goulburn Murray Water

Tungamah Pipeline Project

A major challenge on the project from the outset was the resistance of several key Landowners to joining the scheme threatening to derail the project. Face to face meetings between the Landowners and Managing Director Wayne Mitchell established Landowner consent for the 40km of pipelines to be constructed through their properties, with access points omitted pending resolution of Water Authority issues.