Project

Koroit Reticulation Sewerage Scheme

23 km of 150 to 300 diam gravity pipeline and rising mains

Project Details

LOCATION

Koroit, VIC

PROJECT VALUE

2.24m

YEAR

1999

CLIENT

South West Water

Related Projects

Westside Corporation

Meridian Seamgas Trunklines

Mitchell was engaged on a Lump Sum EPC basis:

Engineer: including detail design of the pipeline alignments, profiles, road, waterway & service crossings, vents & drains, taking into account landholder constraints, endangered habitat and access issues, and SMS all to APGA CSG Gathering code.

Procure: including the purchase, transport, storage and correct dispatch of all materials and external services providers.

Construct: Install, test and commission the pipelines, and handover As Built GIS and complete MDR.

Santos Ltd

K129 Gathering Pipelines