Merri Abba Bore Pipeline

Installation of 35km of DN300 PVC pipelines, 1 pump station, a 1ML concrete storage tank, treatment facilities and 30km of HV Powerlines.

Project Details

LOCATION

Lake Cargelligo, NSW

PROJECT VALUE

13m

YEAR

2011

CLIENT

Lachlan Shire Council

Related Projects

NSW Department of Commerce

Darling Anabranch Pipeline Project

Grampians Wimmera Mallee Water

Wimmera Mallee Pipeline Project

Major construction challenges included major river crossings, a variety of cultural heritage sites and liaising with some 4,000 property owners.

Mitchell designed and constructed six of the seven supply systems in just over 3 years, delivering the project 6 years ahead of the original 10 year time frame.

Mitchell’s safety performance on the project was outstanding, completing 900,000 manhours without a single LTI.