80km Trenching

Project Details

LOCATION

Sydenham - Bendigo, VIC

PROJECT VALUE

10m

YEAR

2004

CLIENT

John Holland Constructions

Related Projects

Santos Limited

GLNG – Fairview CSG Gathering Lines

Goulburn Murray Water

Tungamah Pipeline Project

A major challenge on the project from the outset was the resistance of several key Landowners to joining the scheme threatening to derail the project. Face to face meetings between the Landowners and Managing Director Wayne Mitchell established Landowner consent for the 40km of pipelines to be constructed through their properties, with access points omitted pending resolution of Water Authority issues.