South West Loddon Pipeline

1300km

Pipelines

11

Pump Stations

15km

HDD Crossings

8

2.5ml Storage Tanks

The South West Loddon Pipeline Project provided a new pressurised raw water pipeline supply system to a farming region of approximately 2,900 km2 located generally to the south of Korong Vale in Victoria. The unprecedented EPC scope required Mitchell to prepare and obtain ministerial approval of all planning documentation, pipeline route selection, environmental and cultural heritage field flora, fauna & cultural surveys, hydraulic design, construction of approximately 1,300km of water pipelines, pump stations, storages and power supply to service more than 600 rural properties.

Project Details

  • Planning Approval (Environment Management Framework Plan, Native Vegetation Offset Strategy, Native Vegetation Offset Plans, Threatened Species Management Plan, Construction and Environmental Management Plan, Project Design Impact Assessment Report including completion of flora and fauna surveys, 5No. Cultural Heritage Management Plans)
  • 1300 km of pipelines up to 450mm DICL, PVC and HDPE
  • Air, isolation, scour outlets & stock offtakes
  • 11 pumping stations including over 40 pump sets
  • SCADA control
  • 8 storage tanks up to 2.5ML
  • 630 meter connections including Firefighting infrastructure
  • 7 metre deep concrete wet well pumping station
  • Warranga Channel offtake
  • Over 15,000m HDD creek and road crossings
  • 25 Rail and Road Thrust Bores up to DN630
  • Landholder liaison (1200 property owners)

LOCATION

North Central, VIC

PROJECT VALUE

80m

YEAR

2019-20

CLIENT

Grampians Wimmera Mallee Water

Related Projects

Grampians Wimmera Mallee Water

Wimmera Mallee Pipeline Project

Major construction challenges included major river crossings, a variety of cultural heritage sites and liaising with some 4,000 property owners.

Mitchell designed and constructed six of the seven supply systems in just over 3 years, delivering the project 6 years ahead of the original 10 year time frame.

Mitchell’s safety performance on the project was outstanding, completing 900,000 manhours without a single LTI.

Evolution Resources PTY LTD

Cowal Gold Water Pipeline

Evolution’s Cowal Operation is located approximately 40km north-east of West Wyalong in New South Wales, Australia. This high-quality Australian gold asset with a long history of stable, large scale, low cost production. The mine pit encroaches the Lake Cowal ephemeral lake system. The lake is approximately 9.5km wide when full.