Project

South West Loddon Stock and Domestic Water Scheme _ Stage 1

110 km of pipelines ranging from 315 mm to 63mm, 3 Pump Stations, 3 water storage tanks of 1ML each

Project Details

LOCATION

Charlton, VIC

PROJECT VALUE

5.4m

YEAR

2016

CLIENT

Grampians Wimmera Mallee Water

Related Projects

Westside Corporation

Meridian Seamgas Trunklines

Mitchell was engaged on a Lump Sum EPC basis:

Engineer: including detail design of the pipeline alignments, profiles, road, waterway & service crossings, vents & drains, taking into account landholder constraints, endangered habitat and access issues, and SMS all to APGA CSG Gathering code.

Procure: including the purchase, transport, storage and correct dispatch of all materials and external services providers.

Construct: Install, test and commission the pipelines, and handover As Built GIS and complete MDR.

BMD Construction

Middlemount Coal Pipeline

The Middlemount Coal Mine (Mine) is an open cut coal mine located approximately 270 km west-northwest of Rockhampton and approximately 10 km south west of the township of Middlemount. The work was required to be performed both ON & OFF mine lease for Peabody Energy and Yancoal Australia.