Supply and Construction of Stawell _ Landsborough Valley Water Pipeline

26km, 12km install and 14km rectification, pipeline designed to convey raw water from the Reservoir at Stawell to vineyards in the Landsborough Valley and 6 swabbing stations

Project Details

LOCATION

Stawell, VIC

PROJECT VALUE

1.5m

YEAR

2015

CLIENT

Grampians Wimmera Mallee Water

Related Projects

Grampians Wimmera Mallee Water

Wimmera Mallee Pipeline Project

Major construction challenges included major river crossings, a variety of cultural heritage sites and liaising with some 4,000 property owners.

Mitchell designed and constructed six of the seven supply systems in just over 3 years, delivering the project 6 years ahead of the original 10 year time frame.

Mitchell’s safety performance on the project was outstanding, completing 900,000 manhours without a single LTI.

Westside Corporation

Meridian Seamgas Trunklines

Mitchell was engaged on a Lump Sum EPC basis:

Engineer: including detail design of the pipeline alignments, profiles, road, waterway & service crossings, vents & drains, taking into account landholder constraints, endangered habitat and access issues, and SMS all to APGA CSG Gathering code.

Procure: including the purchase, transport, storage and correct dispatch of all materials and external services providers.

Construct: Install, test and commission the pipelines, and handover As Built GIS and complete MDR.