Project

Supply and Construction of Stawell _ Landsborough Valley Water Pipeline

26km, 12km install and 14km rectification, pipeline designed to convey raw water from the Reservoir at Stawell to vineyards in the Landsborough Valley and 6 swabbing stations

Project Details

LOCATION

Stawell, VIC

PROJECT VALUE

1.5m

YEAR

2015

CLIENT

Grampians Wimmera Mallee Water

Related Projects

Grampians Wimmera Mallee Water

South West Loddon Pipeline

Goulburn Murray Water

Tungamah Pipeline Project

A major challenge on the project from the outset was the resistance of several key Landowners to joining the scheme threatening to derail the project. Face to face meetings between the Landowners and Managing Director Wayne Mitchell established Landowner consent for the 40km of pipelines to be constructed through their properties, with access points omitted pending resolution of Water Authority issues.