Project

Darling Anabranch Pipeline Project

320km

Pipelines

8

Months to Build

Zero

LTI’s

2

Pump Stations

The DAPP comprised of full design, supply, construction, commissioning, provision of operations manuals and training of the 320km stock and domestic system in remote rural farming area of western NSW, including 2 pump stations, river intakes and lagoons. Mitchell employed a large number of Indigenous personnel on the project and the Aboriginal Participation in Construction Guidelines (NSW) were written on the basis of this project. Mitchell delivered the project in 8 months, some 4 months ahead of schedule with zero LTI’s.

Project Details

  • 320km of pipelines 375-50mm in diameter
  • 2 Pumping stations, including buildings, mechanical, electrical and software
  • River intakes
  • Lagoons
  • Hydraulic System Analysis
  • Survey, design and As-Constructed plans
  • Commissioning, provision of Operating Manuals and Training

LOCATION

Menindee, NSW

PROJECT VALUE

54m

YEAR

2006

CLIENT

NSW Department of Commerce

Related Projects

Santos Limited

Roma West 2B Gathering Project

This particular section included gas and water gathering pipelines, along with the added complexity of installation of HV & FOC reticulation, often commingled within the trenches with the PE Gas & Water pipelines.

Pneumatic testing was progressively completed in five defined sections, allowing a sequenced handover of the asset to commence early gas extraction.

Completed on time and on budget, with zero defects, despite significant challenges of slow rock excavation and inclement weather.