Mallee Towns Drinking Water Pipeline Project

132km

Pipelines

3

Pump Stations

6

Storage Tanks

53

New Jobs Created

The pipeline was constructed to deliver drinking water from the Warracknabeal Water Treatment Plant to Sea Lake, via townships Brim, Beulah, Hopetoun and Woomelang. The water previously piped to these townships was untreated and deemed unsuitable for consumption meaning all households had to provide their own rainwater water.

As with all projects Mitchell undertake, the Mallee Towns Drinking Water Pipeline contributed greatly to the local economy and jobs sector. In conjunction with the South West Loddon Pipeline Project, Mitchell committed to carry out works under the Local Jobs First, Victorian Industry Participation Plan. Some 53 new jobs were created, 5 new apprenticeships and works helped promote business growth and employment by expanding market opportunities for the local small and medium enterprise industry.

Project Details

  • 132 km of DN200-225 PVC pipelines
  • 3 pump stations
  • 2 x 2.4ML Water Storage tanks
  • 2 x 1.8ML Water Storage tanks
  • 2 x 1ML Water Storage tanks
  • Road and water crossings

LOCATION

Beulah, VIC

PROJECT VALUE

17m

YEAR

2017-18

CLIENT

Grampians Wimmera Mallee Water

Related Projects

Santos Limited

Roma West 2B Gathering Project

This particular section included gas and water gathering pipelines, along with the added complexity of installation of HV & FOC reticulation, often commingled within the trenches with the PE Gas & Water pipelines.

Pneumatic testing was progressively completed in five defined sections, allowing a sequenced handover of the asset to commence early gas extraction.

Completed on time and on budget, with zero defects, despite significant challenges of slow rock excavation and inclement weather.

Santos Limited

Santos Pre-field Development

The Narrabri project, although short in length and duration was very challenging due to the alignment of the pipeline being the middle of the Pilliga State Forrest, within an existing HDPE Water line corridor, with no new clearing allowed. The pipeline was subject to strict EIS conditions including minimising dust and erosion onsite. To manage the conditions an extensive erosion sediment control plan (ESCP) was designed and implemented.