Bingegang Pipeline Realignment

A new 14km pipeline to replace the existing pipeline. Includes a Break Tank, 66KV OHL, Pump Station, salvage and reuse of existing infrastructure as nominated, outlets, crossings, associated local drainage provisions, fencing and maintenance access infrastructure.

Project Details

LOCATION

Bingegang, QLD

PROJECT VALUE

7m

YEAR

2015

CLIENT

BMD Constructions

Related Projects

Santos Limited

Roma West 2B Gathering Project

This particular section included gas and water gathering pipelines, along with the added complexity of installation of HV & FOC reticulation, often commingled within the trenches with the PE Gas & Water pipelines.

Pneumatic testing was progressively completed in five defined sections, allowing a sequenced handover of the asset to commence early gas extraction.

Completed on time and on budget, with zero defects, despite significant challenges of slow rock excavation and inclement weather.

NSW Department of Commerce