Project

Middlemount Coal Pipeline

The construction of a 14km pipeline was to replace the existing pipeline for the Middlemount Coal Mine. The works included a break tank, 66KV OHL, pump station, salvage and will reuse the existing infrastructure including, outlets, crossings, associated local drainage provisions, fencing and maintenance access infrastructure.

The Middlemount Coal Mine (Mine) is an open cut coal mine located approximately 270 km west-northwest of Rockhampton and approximately 10 km south west of the township of Middlemount. The work was required to be performed both ON & OFF mine lease for Peabody Energy and Yancoal Australia.

Project Details

  • Construct 14km’s DN450mm DICL pipe
  • Air, isolation, scouroutlets and stockofftakes
  • Pumping Station pipework and pump manifolds
  • Fabrication and install air valves
  • Fabrication and install scour outlets
  • Installation of pipe work for swab control and non-return structure, balance tank inlet and outlet pipework

LOCATION

Middlemount, QLD

PROJECT VALUE

12m

YEAR

2015

CLIENT

BMD Construction

Related Projects

Grampians Wimmera Mallee Water

Wimmera Mallee Pipeline Project

Major construction challenges included major river crossings, a variety of cultural heritage sites and liaising with some 4,000 property owners.

Mitchell designed and constructed six of the seven supply systems in just over 3 years, delivering the project 6 years ahead of the original 10 year time frame.

Mitchell’s safety performance on the project was outstanding, completing 900,000 manhours without a single LTI.

Carmichael Rail Network

Carmichael Rail Pipeline

The Carmichael coal mine is located in the north Galilee Basin, Queensland, approximately 280km south of Townsville and 300km west of Mackay. The work scope included the construction of a water pipeline and procurement of associated pumping equipment & water storages.